Observation 3 with LIGO/Virgo (2019-2020)
|
Back to the KSC top page / wiki top page |
|
The page is maintained by KAGRA Scientific Congress (KSC) |
Schedule, Organization, Commitment form, Links
Schedule
- March 4, 2019: LV starts ER14.
- April 1, 2019: LV starts O3.
Organization (Joint Committees with LIGO/Virgo)
KSC organization chart is available at here
O3 Commitment form
- KSC decided to collect a commitment form from every KAGRA collaborators before O3 starts.
- The purpose of this Agreement is to establish and recognize the fundamental rules and policies between each colleague and the KAGRA collaboration for participating joint observation run 3 (O3) with LIGO/Virgo collaborations, starting from April 2019.
The form is available from JGWdoc-M1909631.
- You are supposed to download the form, print it, sign it, scan it, edit the file name, and submit it.
Submission page is https://gwcenter.icrr.u-tokyo.ac.jp/o3-commitment-form