 . Commissioning schedule from [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]]  . Commissioning schedule from [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]][[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5692|JGW-T1605692]]

bKAGRA Calibration Tasks and people

Phase1 (before the deadline: Mar/2017)

Before ETMY CRYp installation

  • CAL Task: Lab test on the CRYp actuators

  • People: Miyamoto, Ushiba, Inoue, Tomaru +CRY

2017.10.31 ETMY CRYp installed

  • Return the beam from ETMY to BS
  • CAL Task: What we can do for the calibration with a single arm ?

2017.11.22- ETMY evacuation

2017.12.8 cool down starts

  • CAL Task: ETMY monitoring with HR-camera

  • People: Inoue, Haino +CRY

2018.2.2 ETMX CRYp installed

  • Return the beam from ETMX to BS
  • Lock room temperature Michelson
  • CAL Tasks:
  • Measurement of optical efficiency

  • Measurement of open-loop transfer function

  • Implementation of online h(t) generator

  • People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS

2018.2.13- ETMX evacuation

2018.3.2 cool down starts

  • CAL Tasks:
  • Monitor of actuator efficiency during cool down

  • ETMX monitoring with HR-camera

  • People: Miyamoto, Ushiba, Inoue, Haino, Tomaru +CRY

By 2018.3.31 Start observation run with 3-km cryogenic Michelson

  • CAL Tasks:
  • Measurement and evaluation of time variation of optical and actuator efficiencies

  • In which frequency we should excite the calibration lines ?

  • People: Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS subgroups

Phase1 (after the deadline: Mar/2017)

  • Shorten PR2-PR3 length by 2.4 cm (at max)
  • Re-alignment
  • connect remaining bellows/ducts and evacuate central area
  • Lock cryogenic PRMI
  • Cal Tasks: Redo the calibration

  • Measurement of optical efficiency

  • Measurement of open-loop transfer function

  • People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS