bKAGRA Calibration Tasks and people

Phase1 (before the deadline: Mar/2017)

Before ETMY CRYp installation

2017.10.31 ETMY CRYp installed

2017.11.22- ETMY evacuation

2017.12.8 cool down starts

2018.2.2 ETMX CRYp installed

2018.2.13- ETMX evacuation

2018.3.2 cool down starts

By 2018.3.31 Start observation run with 3-km cryogenic Michelson

Phase1 (after the deadline: Mar/2017)