Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/10/22 13:00-
Participants:
Schedule
- IX: Health check. F0 actuator.
- EX: Health check. HPCD. BF damper (V).
- IY: LVDT driver. Cable check.
- EY: F0 FR range. Weight on PF.
Status
- TM height setting: ITMY
- ACC: Ready to install to EX. Measurement for IY is necessary.
- Commissioning in air: Health check.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: Under the bidding process.
- Heater control: To PRs in the next.
Discussion
VIS Meeting
Date: 2021/10/22 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: LVDT driver in IY. HPCD and BF damper in EX.
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 10/25
- Takahashi: 10/26-29
- Sato: 10/26-29
- Hirata: 10/25-29
- Yano: 10/25-29
The week from 11/1
- Takahashi: 11/1-2
- Hirata: 11/2-5?
- Yano: 11/1-5
Next meeting
- 2021/10/29(FRI)