Date: 2021/12/3 13:00-
Participants:
Schedule
- IX: Finalization of cryo-payload. Replacement of flip cables.
- EX: Finalization of cryo-payload. Height adjustment of TM.
- IY:
- EY: Some problems (actuators, F0 yaw FR).
Status
- Replacement of flip cables: IX on 12/2.
- TM height setting: ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Driver setup for IY on 12/2. Assembly for EY is ongoing.
- Commissioning in air: Return of GRY.
- Commissioning in vacuum: Chamber closing is scheduled from 12/13.
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control:
- Power source for Oplev: IX.
Discussion
VIS Meeting
Date: 2021/11/26 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Finalization of IX and EX. Recovery of actuators in EY.
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 12/6
- Takahashi: 12/7-10
- Sato: 12/7-9
- Hirata: 12/7-10
The week from 12/13
- Takahashi: 12/13-17
- Sato: 12/13-17
- Hirata: 12/14-17
Next meeting
- 2021/12/10(FRI)