Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/12/17 13:00-
Participants:
Schedule
- IX: Finalization. Closing of the chamber on 12/14. Adjustment of the BFV. Glich in the F3 signals.
- EX: Finalization. Closing of the chamber on 12/15. Pump down on 12/16.
- IY:
- EY: There is a problem (BF touching).
Status
- Replacement of flip cables:
- TM height setting: ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Assembly for EY is under way.
- Commissioning in air: Return of GRY.
- Commissioning in vacuum: Pump down of EXC/EXV on 12/15.
- Overall commissioning:
- Acceptance check: Review on 12/10.
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: TMP to IXV and EXC-BRT on 12/13.
- Heater control:
- Power source for Oplev:
Discussion
VIS Meeting
Date: 2021/12/10 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: BF in EY
- Type-B team:
Safety
- The helmet droped from the second floor in the PR2 booth.
Discussion
Travel Plans
(Date in Kamioka)
The week from 12/20
(F2F meeting in 12/20-21)
- Takahashi: 12/22-24
- Sato: 12/22-24
- Hirata: 12/22-24
The week from 12/27
(Holidays in 12/29-1/3)
Next meeting
- 2021/12/24(FRI)