2017/2/22(Thur.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Diagonalizing input matrix. Electronics was something wrong, like oscillation.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- ISS: Koseyama, Kitazawa
- Making RT models.
- ETMY: Enomomoto, Izumi
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Height change for PRs
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Exchanging items and cleaning inside the PR2 chamber
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- Week of 2/19
- Issues