Differences between revisions 1 and 2
Revision 1 as of 2018-02-22 10:05:55
Size: 991
Comment:
Revision 2 as of 2018-02-23 08:57:46
Size: 866
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:

  * BS: Kozu
   * Finished measurement the TF of TM and IM coupling.

  * ISS: Koseyama, Sakamoto.
   * Measuring TF.

2017/2/22(Thur.)

  • Remote participants by eZuce: Miyoki
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • Diagonalizing input matrix. Electronics was something wrong, like oscillation.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • ISS: Koseyama, Kitazawa
      • Making RT models.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
      • Height change for PRs
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Exchanging items and cleaning inside the PR2 chamber
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
  • Issues

KAGRA/Commissioning/DailyWork/2018-02-22 (last edited 2018-02-23 08:57:46 by OsamuMiyakawa)