2017/3/2(Fri.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment: Enomoto, Miyo, Yokozawa
- IMC and IMMT was aligned to center PRs.
- Beam spot was not seen at the end.
- We absolutely need monitors to check beam position at all the mirrors.
- IOO: kokeyama
- Alignment to MC was fixe.
- AOS:
- Lasers of oplev will can be dying soon.
- The lifetime is about 100000h.
- Lasers of oplev will can be dying soon.
- CRY: mirror temperature 89K.
- Alignment: Enomoto, Miyo, Yokozawa
- Work plan (*:responsible person)
- Alignment:
- Alignment to IYA, or IYC will be checked and we will find the spot at the end then.
- Alignment:
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues