2017/3/5(Mon.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment: Enomoto, Miyo, Yokozawa
- We found beam at the IYA but it is not clear PR or BS is misaligned.
- IOO:
- IMMT2 cannot be seen by camera. We will work on camera this week.
- CRY: mirror temperature 71K.
- Alignment: Enomoto, Miyo, Yokozawa
- Work plan (*:responsible person)
- Alignment: Enomoto
- We will find beam at the ETMY or ETMX by dithering PR3.
- BS: Mark
- We lift up the optical table and change items to vacuum compatible one. It does not change BS alignment an oplev.
- Alignment: Enomoto
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues