2017/3/6(Tue.)
- Remote participants by eZuce: Kimura
- Report of work (*:responsible person)
- Alignment: Enomoto
- Beam was found again at PD and Tcam of ETMX and Tcam of ETMY.
- BS: Mark
- We lifted up the optical table.
- IOO:
- IMMT2 cannot be seen by camera. We will work on camera this week.
- CRY: mirror temperature ~40K.
- Alignment: Enomoto
- Work plan (*:responsible person)
- Alignment: Enomoto
- We will find beam at the ETMY or ETMX by dithering PR3.
- AOS: Akutsu, Michimura
- Items PR2 chamber will be replaced, and green light will be used in the afternoon.
- WAB work at the IYA.
- Alignment: Enomoto
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end for both IR and green.
- Weekly
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- week of 3/5
- Issues