2017/3/6(Wed.)
- Remote participants by eZuce: Izumi
Report of work (*:responsible person)
- Alignment: Enomoto, *Izumi
- Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
- AOS: *Akutsu, Michimura
- We replace all the items which were not compatible to vacuum.
- Tcam: *Inoue, Cory, Binhua
- Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
- CRY: mirror temperature 24K.
Work plan (*:responsible person)
- Alignment: *Enomoto
- PD at BS will be moved to REFL.
- Connection of PD signal to DAQ should be implemented this week or next week.
- GigE camera should be placed at the REFL port eventually.
- AOS: *Akutsu, Michimura
- Alignment of green light to ETMY will be finished today.
Laser hazard
- AM: Around PR2 for green, Y-end for IR.
- PM: Around PR2 for green, upstream SR2-3 line for IR.
Weekly
- week of 3/5
- 3/5 Exchanging items and cleaning inside the PR2 chamber
- 3/8 IYC door will be closed.
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues