Size: 1315
Comment:
|
Size: 1313
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== * Alignment: Enomoto, Izumi * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26. |
Line 7: | Line 9: |
* Alignment: Enomoto, Izumi * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26. |
* AOS: Akutsu, Michimura * We replace all the items which were not compatible to vacuum. |
Line 10: | Line 12: |
* AOS: Akutsu, Michimura * We replace all the items which were not compatible to vacuum. |
* Tcam: * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light. |
Line 13: | Line 15: |
* Tcam: * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light. |
* CRY: mirror temperature 24K. |
Line 16: | Line 17: |
* CRY: mirror temperature 24K. | ==== Work plan (*:responsible person) ==== * Alignment: Enomoto * PD at BS will be moved to REFL. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
Line 18: | Line 23: |
* Work plan (*:responsible person) | * AOS: Akutsu, Michimura * Alignment of green light to ETMY will be finished today. |
Line 20: | Line 26: |
* Alignment: Enomoto * PD at BS will be moved to REFL. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. * AOS: Akutsu, Michimura * Alignment of green light to ETMY will be finished today. * Laser hazard: * AM: Around PR2 for green, Y-end for IR. * PM: Around PR2 for green, upstream SR2-3 line for IR. |
==== Laser hazard ==== * AM: Around PR2 for green, Y-end for IR. * PM: Around PR2 for green, upstream SR2-3 line for IR. |
Line 33: | Line 31: |
* Weekly * week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
==== Weekly ==== * week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
Line 38: | Line 36: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 42: | Line 40: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
2017/3/6(Wed.)
- Remote participants by eZuce: Izumi
Report of work (*:responsible person)
- Alignment: Enomoto, Izumi
- Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
- AOS: Akutsu, Michimura
- We replace all the items which were not compatible to vacuum.
- Tcam:
- Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
- CRY: mirror temperature 24K.
Work plan (*:responsible person)
- Alignment: Enomoto
- PD at BS will be moved to REFL.
- Connection of PD signal to DAQ should be implemented this week or next week.
- GigE camera should be placed at the REFL port eventually.
- AOS: Akutsu, Michimura
- Alignment of green light to ETMY will be finished today.
Laser hazard
- AM: Around PR2 for green, Y-end for IR.
- PM: Around PR2 for green, upstream SR2-3 line for IR.
Weekly
- week of 3/5
- 3/5 Exchanging items and cleaning inside the PR2 chamber
- 3/8 IYC door will be closed.
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues