2017/3/8(Fri.)
- Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- Alignment: *Enomoto, Michimura
- Tuning of ETMY damping.
- PD of transmitted light of ETMY was implemented.
- Oplev of are centered.
- Yaw of 0.2Hz of ETMY is still moving. RMS is limited by this ~10urad.
- CRY: mirror temperature started increasing because of turning one of the cryo pump off.
- Tcam: *Inoue, Cory, Binhua
- phi800 door of IX will be closed Monday, IY will be closed Tuesday or Wednesday.
Work plan (*:responsible person)
Laser hazard
- [AM] IR: PSL, Green: PR2.
- [PM] IR: PSL, Green: PR2.
Weekly
- week of 3/5
- 3/8 IYC door will be closed.
- week of 3/12
- 3/14: meeting for pump-down check
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
- GigE camera should be placed at the REFL port eventually.