2017/3/20(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- PR2 assembly frames will be removed soon.
- Alignment: *Izumi
- All alignment to REFL after pump down was verified.
- Only ETMY was off position by ~100urad.
- All alignment to REFL after pump down was verified.
- ETMY: *Miyamoto
- Diagonal of sensors. Still going on.
- BS: Eleonora, Izumi
- Coil balance is going on.
- IMC:
- "sleep" commands were removed from Guardian.
- Cal: Yokozawa
- We checked all the IMC TFs.
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- Cal: Yokozawa
- Injection will be tested soon.
Laser hazard
- [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues