2018/4/5(Thur.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- Alignment: Izumi
- Both light had been confirmed at REFL yesterday morning.
- IR beam was lost at REFL evening, but green was still seen.
- Both IR and green were still seen at Y end.
- ETMX: *Ushiba
- Circuits and connection are still being checked.
- Dolphin: *Yamamoto
- Connected IMC, IOO and BS.
- Error indicator is seen on BS.
- DAQ: *Yamamoto
- Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
- k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
- PCal: no one to report
- TMS: no one to report
Work plan (*:responsible person)
- Alignment: Izumi
- IR will be re-aligned this morning. It requires green off evening.
- ETMY: *Miyamoto
- Cover on Oplev will be set this morning.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
- Vacuum: *Kimura
- Closing door will be performed in the next week.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC