2018/4/6(Fri.)
* Remote participants by eZuce: Kimura
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Both light was confirmed at ETMX last night.
- BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz.
- Connection between k1lsc and k1bs is still something wrong.
- Quality of ETMX looks much better than EMY. No bright spot was seen.
- ETMY: *Miyamoto
- Covered on Oplev.
Work plan (*:responsible person)
- Alignment: Izumi
- No light is used in the daytime. Start using beam from evening.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
- Vacuum: *Kimura
- Closing door will be performed in the next week as planned.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC