2018/4/20(Fri.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • Phase 1 operation was postponed to 4/28 start and 5/6 end.
  • VAC: *Kimura
    • Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
    • Pump down started 15:50 yesterday.
    • Now vacuum gage shows ~30Pa.
  • VAC: *Inoue, Yokozawa
    • Vacuum monitor is ready! except for Y arm monitor.
  • ETMX: *Hasegawa
    • 0.07Hz was damped well!
    • Yaw and pitch are < 1urad.

  • ETMY: *Nakano, Shishido
    • Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
    • Possibility of heat link for 1.6Hz still remains.
    • Beam at REFL seemed to be OK.
  • BS: *Eleonora, Izumi
    • Implementation of L2P filter worked well and they are well decoupled now!
    • Global injection point for length control is ready.

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Leak test will be performed and the gate valve will open on weekend if no problem.
  • Camera: *Inoue, Yokozawa
    • Tcam of Y end will be ready today.
  • We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
    • DMG needs some maintenance for DAQ.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check, and fix leaks.
    • Opening the last gate valve weekend.
  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues