2018/5/1(Tue.)
* Remote participants by eZuce: None * 4th day of Phase 1 operation
- TF of ETMX
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- DAC on PR3: Yamamoto
- PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
- lock lost was ~100min, including guardian misrecording.
- DAQ was dead 2-3min.
- Noise budged: *Tanioka, Izumi, Enomono
- PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
- 100Hz noise seems to be dominated by beam position of BS or ETMY.
- DAC on PR3: Yamamoto
- TF of BS was well done.
- CBC injection was well done.
- DGS: *Miyakawa
- Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.
Work plan (*:responsible person)
- TF of Type A: Okutomi, Miyamoto
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.