2018/5/6(Sun.)
- Remote participants by eZuce: None
- 9th day of Phase 1 operation
- PEM vibration injection
- PEM sound injection
- Hammer injection
Report of work (*:responsible person)
- IFO: *Enomoto + many
- Consorts bad yesterday and day before yesterday.
- Lock was stable agin after evening of yesterday.
- Shunup asymmetry: Enomoto
- Result: asymmetry was estimated 3.8+/-1.4m.
- It will be measured this morning again to reduce error bar.
Work plan (*:responsible person)
- IFO: *Enomoto + many
- PEM/CRY hammering test.
- PEM sound injectio.
- OLG: Yamamoto
- OLG measurement with full swinging.
- Type A: Miyamoto
- End IM TF
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
- week of 5/7
- 5/7 8-9am: Close 7 gate valves.