2018/8/22(Wed.)
- PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
- Actual night work will start 9/3 (9/1, 9/2 are weekends).
- We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
- One Car (Serena) will be assigned to commissioning work.
Attendance
- Control room: Miyakawa, Akutsu, Yamamoto, Yokozawa, Enomoto
- Fan hut:
- educe: Kokeyama
Transition from morning work (*:responsible person)
Report of work (*:responsible person)
- Illuminator was not finished, it will be installed Tomorrow. '(Yokozawa)
- ALS rack is being prepared. (Enomoto)
- NAB white tape was removed.
- IP of ITMX was released and tuned.
Work plan (*:responsible person)
- MC will be restored today.