2018/8/27(Mon.)
- PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
- Actual night work will start 9/3 (9/1, 9/2 are weekends).
- We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
- One Car (Serena) will be assigned to commissioning work.
Attendance
- Control room: Enomoto, Miyakawa, Ushiba
- Fan hut:
- educe:
Transition from morning work (*:responsible person)
Report of work (*:responsible person)
- Alignment procedure was updated.
Work plan (*:responsible person)
- Watchdog of 4 coil driver for CRY should be removed.