2018/9/6(Thur.)
- How about the day and night work on Saturday or Sunday.
Attendance
- Control room: Izumi, Akutsu, Anna
- Fan hut: Miyakawa, Takahashi(ICRR), Enomoto, Yokozawa, Kimura, Ueda
- eZuce:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Izumi, Enomoto, Eleonora
Transition from morning work (*:responsible person)
- ETMY rack was stopped.
Report of work (*:responsible person)
- Cleaning cable of ETMY rack was done.
- DAC made 1Hz sound at the PSL.
- IMC did not work yesterday. Changing some gain and threshold made lock.
- This morning FSS did not work again.
Work plan (*:responsible person)
- We will introduce beam up to BS.