2018/9/7(Fri.)
- How about the day and night work on Saturday or Sunday?
Attendance
- Control room: Miyakawa, Eleonora. Licia, Fujii
- Fan hut: Izumi, Takahashi(ICRR), Enomoto, Izumi, Akutsu
- eZuce: Yokozawa
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Izumi, Enomoto, Eleonora, Yokozawa
Transition from morning work (*:responsible person)
- ETMs, ITMs, BS, SR2 will be shutdown this afternoon.
- PRMs and SR3, SRM will be shutdown later.
- Laser will shutdown later.
Report of work (*:responsible person)
- Clean up the fiber coupler for ALS.
- FSS did not work and it was tuned by Nakano and got locked.