2018/9/13(Thur.)
- We do not have a commissioning work tomorrow (9/14), but we may have commissioning work weekend (9/15-17).
Attendance
- Control room: Miyakawa, Kozakai, Inoue
- Fan hut: Furuta, Saito, Enomoto, Michimura, Takeda, Yokogawa, Sugimoto, Kokeyama
- eZuce:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR |
IR |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Enomoto, Michimura, Takeda, Yokogawa, Sugimoto, Kozakai, Darkhan, Inoue
Transition from morning work (*:responsible person)
- IOO people work for MZ and ASC this afternoon. Thew work until 3pm.
Report of work (*:responsible person)
Work plan (*:responsible person)
- Beams will reach X end today.
- Floor coating will be done in the weekend of the end of September.