2018/9/27(Thur.)
Attendance
- Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa
- Fan hut: Furuta
- eZuce:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka
- CAL: Kozakai, Ogai, Tomaru
Transition from morning work (*:responsible person)
- Measurement of ETMX is going on until 3pm.
Report of work (*:responsible person)
- EYA is opening now.
Work plan (*:responsible person)
- Need ETMX calm, so AC will be stopped.