Site Work Summary | ==== Attendance ==== * Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa * Fan hut: Furuta * eZuce: ==== Laser hazard ==== |||| ||Before 3PM||After 3PM || |||| || |||| ||Center||PSL ||IR & Green||IR & Green|| ||Center||upstream IMM ||IR ||IR || ||Center||around PR2 ||IR & Green||IR & Green|| ||Center||behinde SR2-3 line||N/A ||IR & Green|| ||||X end 1F ||N/A ||IR & Green|| ||||Y end 1F ||N/A ||N/A || ==== Night workers ==== * Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka * CAL: Kozakai, Ogai, Tomaru ==== Transition from morning work (*:responsible person) ==== * Measurement of ETMX is going on until 3pm. ==== Report of work (*:responsible person) ==== * EYA is opening now. ==== Work plan (*:responsible person) ==== * Need ETMX calm, so AC will be stopped. |
2018/9/27(Thur.)
Attendance
- Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa
- Fan hut: Furuta
- eZuce:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka
- CAL: Kozakai, Ogai, Tomaru
Transition from morning work (*:responsible person)
- Measurement of ETMX is going on until 3pm.
Report of work (*:responsible person)
- EYA is opening now.
Work plan (*:responsible person)
- Need ETMX calm, so AC will be stopped.