2018/10/10(Tue.)
Attendance
- Control room: Miyakawa, T.Tanaka, Yamamoto, Kozakai, Tanioka
- Fan hut: Kokeyama, Akutsu
- eZuce: Enomoto
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
N/A |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
IR |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Commissioning: Enomoto, Ushiba, Miyoki
- CAL: Kozakai, Yamamoto
- AOS: Akutsu, Tanaka, Michimura,Zimon
- IOO: Tanioka
Weekend
Transition from morning work (*:responsible person)
- EXA PD was removed.
Report of work (*:responsible person)
- WAB finalization will be start this evening or tomorrow morning.