2018/10/18(Thur.)
Attendance
- Control room: Miyakawa, Yamamoto, Yuzurihara, Miyo, nakano, Tanaka, Yokozawa, Oshino, Dankan, Lucia, Fujii, Yokogawa, Enomoto, Kokeyama
- Fan hut:
- eZuce:
- Zoom: Hayakawa
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2&Yfront |
IR |
IR |
X end 1F |
IR & Green |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- MIF: Enomoto, Yokogawa, Kozakai
Weekend
Transition from morning work (*:responsible person)
- IPs of ETMX are freely moving. Oplev at ETMX has still no light.
- ITMX alignment seems to be fine already. We can see green light at REFL port.
- Leak test is going on.
Report of work (*:responsible person)
- KAGRA summary pages are available now.
Work plan (*:responsible person)
- Green is hitting ETM. Alignment of ITM will be done.
- Needs damping of ITMX and ETMX.
- Marionet oplev light are not existing for both ITMX/ETMX.