2018/10/26(Fri.)
- Crane inspection around such time: Laser is stopped at output of PSL during the inspection.
Attendance
- Control room: Miyakawa, Yamamoto, Izumi, Lucia
- Fan hut:
- eZuce:
- Zoom:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2&Yfront |
IR |
IR |
X end 1F |
IR & Green |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- MIF:
Weekend
- CAL: Haino, Nakano
Transition from morning work (*:responsible person)
- Magnet of the ETMX seems to be removed. We need to open one day for the DARM feedback. It will a loss of 2weeks.
Report of work (*:responsible person)
- Tidal compensation path was implemented.
- Lock does not last so long. Pitch of ETMX has still large motion.
Work plan (*:responsible person)
- Damping.
- Check network for Pico motor.