2018/11/22(Thur.)
Attendance
- Control room: Miyakawa, Nakano, Kozakai, Yokogawa, Sugimoto, Lucia, Oshino, Yoshioka
- Fan hut:
- Zoom: Enomoto
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
|
|
Center |
PSL |
IR & Green |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2&Yfront |
IR |
IR |
X end 1F |
IR & Green |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers in the mine
- MIF: Enomoto, Yokogawa, Sugimoto, Yamamoto, Nakano
Weekend
- MIF: (Friday, Saturday, Sunday) Enomoto, Yamamoto
- CAL: (Friday) Kozakai, Inoue, Yamamoto, Yokozawa, Darhan
Transition from morning work (*:responsible person)
Report of work (*:responsible person)
Work plan (*:responsible person)
- MIF: Inject noise to shake optical table or fiber to see the control signal.
- PCAL: Tcam work. Preparation for injection test.
- PCAL: Long term injection starts tomorrow moring.