2018/11/28(Wed.)
- High power laser will be used until ~3pm.
Attendance
- Control room: Lucia, Yamamoto, Kozu
- Fan hut: Ushiba, Enomoto, Yokogawa, Sugimoto, Nakano
- Zoom: Miyakawa, Oshino
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
|
|
Center |
PSL |
IR & Green |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2&Yfront |
IR |
IR |
X end 1F |
IR & Green |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers in the mine
- MIF: Enomoto, Miyoki, Sugimoto, Yokogawa, Nakano, Miyazaki
- CAL: Kozakai, Ogaki
Weekend
Transition from morning work (*:responsible person)
Report of work (*:responsible person)
- Fluctuation of IR became much better because of FPU off.
Work plan (*:responsible person)
- Trial of lock for IR.