2019/1/4(Fri.)
Attendance
- Control room:
- Fan hut:
- Zoom:
Weekend
- COM: Miner measurement.
- VIS: TF of Tye A.
Transition from morning work (*:responsible person)
- Daily commissioning meeting at 1pm moved to 9am.
- Temperature seems to be equilibrium.
- PEM: Channel name assignment should be discussed. Ondotori will be added for new racks.
Report of work (*:responsible person)
- COM: Characterization of ALS. Open loop noise with lock of IR.
- 1day long lock.
- VIS: TF of Tye A.
- Pcal: noise debug.
- PEM: measurement for radio frequency.
Work plan (*:responsible person)
- COM: Miner measurement.
- Team will be tuned for the NIKON camera.