2019/1/21(Mon.)
Weekend
Transition from morning work (*:responsible person)
- Haibo starts joining commissioning work. He will stay 20days.
Report of work (*:responsible person)
- BS: something may be touching or some one of the actuation is not available. It was known by TF measurement.
- GEO phone was something wrong, and it was replaced and it will be checked soon.
- SR3(dust) and SR2(FC is left) is something dirty. Hirose-san will look at it on Tuesday.
- COMM: PD installation at Yend.
- IR and Green reached to ETMX.
- It was found that PR3 surface was dirty. Hirose-san will look at it on Tuesday.
- Ondotori was something wrong. Connector of power supply may be broken. It will be checked by Yokozawa-kun soon.