2019/1/28(Mon.)

Weekend

Transition from morning work (*:responsible person)

  • Schedule
    • Current status as of 1/22: IR and Green reached X end PD.
    • 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.

    • 1/22 or 23 Surface inspection for SR mirrors.

    • 1/24-25 Cleaning HR of SRs.

    • 1/23 BS is aligned to Y-end PD by IR.

    • 1/24-25 ITMY is aligned to REFL by IR.

    • 1/24-25 ITMX is aligned to REFL by IR.

    • 1/24-25 Beam position of IR at SR3 is confirmed how far from the center.

    • 1/28-29 SR3 is aligned to SR2 center by IR.
    • 1/30 Green beam is injected from SR2 AR surface to Y end PD.

    • 1/31-2/1 Removing bellows at PR and SR area.
    • 1/31-2/1 Cleaning HR of PR3 and AR of SR2
    • 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR

    • 2/4-8 Alignment of ETMY -> POS by Green

    • 2/12-15 Closing door for central area, pumping down
      • needs drift monitor for VIS

Report of work (*:responsible person)

  • COM: ITMX and ITMY are aligned and beam was reached to REFL.
    • Beam back from ITMY has hit SR3.
  • COM: Green beam was injected from SR and hit almost center of SR3.
  • ITYM picomotor is not working.

Work plan (*:responsible person)

  • IOO: Needs time to install cables for thermo meter for high power damp. Maybe today, or tomorrow.
  • SRs: needs tuning for damping on Thursday Friday.

KAGRA/Commissioning/DailyWork/2019-01-28 (last edited 2019-01-28 11:52:51 by OsamuMiyakawa)