2019/2/28(Thur.)
Schedule
- Center
2/26-27: Venting
- 2/28: Fixing PRM, PR3 and SRM
- 2/29-5: Re-alignment
- 3/5-6: Closing
- Yend
1/25-2/20: Yend Pcal finalization
- 2/25-3/4: Yend WAB finalization
- 3/5-6: Closing
- 3/6~ : Yend pumpdown 3/6~
- 3/7,8: leak test
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
- 2/23-3/10: Xend Pcal finalization 1
- Periscope installation
- Beam position by IR and Green
- 2/27: ETMX release
- 3/5: ETMX aligned
- 3/5-3/10: Xend Pcal finalization 2
- 3/11,12 Xend WAB finalization
- 3/19,20, Heatlink etc.
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work starts
- 2/18-3/22 DRMI commissioning
- 3/11-4/5 Y arm commissioning
- 3/25-4/5 FPMI commissioning
Note
- Takoyaki party at 6pm.
Weekend
Report of work
- PRM: Vibration measurement of cooler.
- DGS: replaced RTPC of BS to V4 and PRM to V3.
Work plan
- VIS: Fixing PRM, PR3 and SRM
- COM: Alignment of central area after tomorrow.