2019/3/20(Wed.)
Schedule
- Center
2/26-27: Venting
- 2/28-3/15: Health check and maintenance for VIS
PRM: One flag was dropped. -> leave it
3/4-14 PRM: Misalignment does not reach where beam hits damper.
3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.
3/15: BS: Yaw offset adjustment by hand. -> 3/5-6
3/12: BS ok
3/15: some SRs work
3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.
3/18: Re-alignment
- 3/19-21: Closing
- 3/22: pump down
- ITMX:
- 3/19: Cooling stop
- 3/28: Opning chamber
- 3/28: Fixing thermal touch
- 3/29: closing chamber and start pumping down.
- 4/1: Start cooling.
- Xend
1/25-2/20: Yend Pcal finalization
3/5: EYA remaining works by Enomoto, Inoue.
2/25-3/5: Yend WAB finalization
3/6: Y end closing (no laser hazard at least in the morning)
3/7: Y end pump down
- 3/21: leak test
- 3/27: cooling start
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
2/27: ETMX release
2/23-3/6: Xend Pcal finalization 1
Periscope installation
3/6: Beam position by IR and Green
3/5 AOS: EY and EX(if they have time) work.
3/6: Green X alignment (no IR), and no hazard at Y end.
- 3/11, 20: Xend WAB finalization.
3/11~3/15: ETMX tuning.
- 3/19: Heatlink etc.
3/19: ETMX finalization by Takahashi
3/18 : ETMX alignement
- 3/23-24: Pcal alignment
- 3/25: closing
- 3/26: Pumping down
- 4/2-4: Leak test
- 3/27: Cooling start
- 3/25~ : Night work officially starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- 2/18-2/22: PRMI commissioning
- Middle of April~?: DRMI commissioning
- 3/25-middle of May: Y arm commissioning
- Middle of May~: FPMI commissioning
Note
- Night work does not start from 3/11 due to the 2weeks delay by VIS troubles.
- It does not mean that night work is prohibited but it means that officially night shift responsible person won't be assigned and we have no daily meeting at 1pm.
- Official night work starts 3/18 or 3/25, but not determined yet.
Weekend
Report of work
- COM: Alignment was done by the night of day before yesterday.
- Type A:
- ETMX has been confirmed that it is healthy.
- ETMY: IP was something wrong and still alignment was not finished day before yesterday.
- Motor had some problem, and it will be fixed.
- Type B: SR2 oplev is being tuned in these days.