Line 44: Line 44:
  * 3/11, 18,19: Xend WAB finalization.   * 3/11, 20: Xend WAB finalization.
Line 47: Line 47:
  * 3/19: ETMX finalization by Takahashi
  * 3/18,19: ETMX alignement
  * --(3/19: ETMX finalization by Takahashi)--
  * --(3/18 : ETMX alignement)--
Line 55: Line 55:
 * 3/18~ : Night work starts, daily meeting will be moved to 1PM  * 3/25~ : Night work officially starts, daily meeting will be moved to 1PM
Line 59: Line 59:
 * 3/25~?: DRMI commissioning
 * 3/25-4/19: Y arm commissioning
 * 3/25-4/19: FPMI commissioning
 * Middle of April~?: DRMI commissioning
 * 3/25-middle of May: Y arm commissioning
 * Middle of May~: FPMI commissioning

2019/3/20(Wed.)

Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/15: Health check and maintenance for VIS
      • PRM: One flag was dropped. -> leave it

      • 3/4-14 PRM: Misalignment does not reach where beam hits damper.

      • 3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.

      • 3/15: BS: Yaw offset adjustment by hand. -> 3/5-6

        • 3/12: BS ok

      • 3/15: some SRs work

    • 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.

    • 3/18: Re-alignment

    • 3/19-21: Closing
    • 3/22: pump down
  • ITMX:
    • 3/19: Cooling stop
    • 3/28: Opning chamber
    • 3/28: Fixing thermal touch
    • 3/29: closing chamber and start pumping down.
    • 4/1: Start cooling.
  • Xend
    • 1/25-2/20: Yend Pcal finalization

    • 3/5: EYA remaining works by Enomoto, Inoue.

    • 2/25-3/5: Yend WAB finalization

    • 3/6: Y end closing (no laser hazard at least in the morning)

    • 3/7: Y end pump down

    • 3/21: leak test
    • 3/27: cooling start
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/6: Xend Pcal finalization 1

      • Periscope installation

      • 3/6: Beam position by IR and Green

    • 3/5 AOS: EY and EX(if they have time) work.

    • 3/6: Green X alignment (no IR), and no hazard at Y end.

    • 3/11, 20: Xend WAB finalization.
    • 3/11~3/15: ETMX tuning.

    • 3/19: Heatlink etc.
    • 3/19: ETMX finalization by Takahashi

    • 3/18 : ETMX alignement

    • 3/23-24: Pcal alignment
    • 3/25: closing
    • 3/26: Pumping down
    • 4/2-4: Leak test
    • 3/27: Cooling start
  • 3/25~ : Night work officially starts, daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • 2/18-2/22: PRMI commissioning
  • Middle of April~?: DRMI commissioning
  • 3/25-middle of May: Y arm commissioning
  • Middle of May~: FPMI commissioning

Note

  • Night work does not start from 3/11 due to the 2weeks delay by VIS troubles.
    • It does not mean that night work is prohibited but it means that officially night shift responsible person won't be assigned and we have no daily meeting at 1pm.
    • Official night work starts 3/18 or 3/25, but not determined yet.

Weekend

Report of work

  • COM: Alignment was done by the night of day before yesterday.
  • Type A:
    • ETMX has been confirmed that it is healthy.
    • ETMY: IP was something wrong and still alignment was not finished day before yesterday.
      • Motor had some problem, and it will be fixed.
  • Type B: SR2 oplev is being tuned in these days.

Work plan