2019/4/10(Wed.)
Schedule
- Center
3/25: Venting
- 3/27-4/9: Fixing PR2
4/4 -4/5: Gluing
- 4/8: alignment check
- 4/8-10: OSEM adjustment
- 4/11-12: Closing
- 4/12: Pump down
- 4/15~: Leak check
- ITMX:
3/19: Cooling stop
3/25: Venting start
3/27: Opning chamber
3/27~: Fixing thermal touch
4/2~: closing chamber and start pumping down
- 4/12: Cooling starts.
- Xend
3/25: closing and pump down
4/8: Leak check
- 4/9-10: venting
- 4/11: Exchange a broken LED for Photo sensor
- 4/12: closing chamber and start pumping down
- 4/15: Leak check
- 4/19(or 22): Cooling start
- Yend
3/26: Venting start
3/28~: Fixing short inside chamber
4/3: Fixing F0 actuator
4/4~: closing chamber and start pumping down.
- 4/12: Cooling starts.
- 4/8: Daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- April: Measurement of TF, payload diagonalization on ITMX
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Note
- Commissioning meeting moves at 1PM from this week.
Night work
- IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)
Weekend
Report of work
- DC position IP of SR3 is still not good. It will be fixed this morning with IFO alignment.
- OSEM of PRM are fine now. PR2 and SR2 will be tuned today.
PR3 was kicked again this morning -> alignment was fixed.
- Yaw of BS should be offloaded this morning.
Work plan
alignment -> done during morning meeting, BS offload.
- OSEM for PR2.
- OSEM for SR2.
- No maintenance will be done due to above works, specially there is a possibility that exchanging PCs will disturb PRMs and SRMs.
- Tonight MIF will try IFO alignment again for the final check. It hopefully will be done tonight, but laser hazard is assigned all the day tomorrow in the case.
- IOO: iMC ASC work.