2019/4/10(Wed.)

Schedule

Note

Night work

Weekend

Report of work

Work plan

  1. alignment -> done during morning meeting, BS offload.

  2. OSEM for PR2.
  3. OSEM for SR2.
  4. No maintenance will be done due to above works, specially there is a possibility that exchanging PCs will disturb PRMs and SRMs.
  5. Tonight MIF will try IFO alignment again for the final check. It hopefully will be done tonight, but laser hazard is assigned all the day tomorrow in the case.
  6. IOO: iMC ASC work.