2019/4/10(Wed.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2
      • 4/4 -4/5: Gluing

      • 4/8: alignment check
      • 4/8-10: OSEM adjustment
    • 4/11-12: Closing
    • 4/12: Pump down
    • 4/15~: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/12: Cooling starts.
  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting
    • 4/11: Exchange a broken LED for Photo sensor
    • 4/12: closing chamber and start pumping down
    • 4/15: Leak check
    • 4/19(or 22): Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/12: Cooling starts.
  • 4/8: Daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • Commissioning meeting moves at 1PM from this week.

Night work

  • IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)

Weekend

Report of work

  • DC position IP of SR3 is still not good. It will be fixed this morning with IFO alignment.
  • OSEM of PRM are fine now. PR2 and SR2 will be tuned today.
  • PR3 was kicked again this morning -> alignment was fixed.

  • Yaw of BS should be offloaded this morning.

Work plan

  1. alignment, BS offload.
  2. OSEM for PR2.
  3. OSEM for SR2.
  4. No maintenance due to above works.