 * Type A: RT model was separated to two parts for ETMX and ITMX. It needs more time today.  * Type A: RT model was separated to two parts for ETMX and ITMX. It needs more time today. dackill should be implemented in both model.
 * Off loaded FS for BS.

2019/5/27(Mon.)

Schedule

  • 5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS)

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

    • 5/29: Cooling done
  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

Report of work

  • COM: Finesse of Yarm was ~1200 with 60K of ITMY that is a bit lower than expected value even it was estimated by 10% lower ITM reflectivity.
  • CRY: Temperature of ITMY will go lower from above results to distinguish ITMY contamination effect.
  • CRY: Cooler for shield for all 4 test mass, and cooler for payload for ITMY and ITMX and ETMX are working.

Work plan

  • Type B: Needs tuning for BS SR3.
  • Type A: RT model was separated to two parts for ETMX and ITMX. It needs more time today. dackill should be implemented in both model.
  • Off loaded FS for BS.