2019/6/4(Tue.)
Schedule
5/22-23: MZ release from PSL
5/20-24: Exchanging cryo valves.
5/27-6/2: Y arm mass lock. (not done yet)
5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)
- 6/3-6/14: Installation of TMS for ETMY
- 6/8: Engineering run
- ITMX
5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm
5/22AM~: tuned off shield cooler, finesse measurement for Xarm
- ETMX
5/2: Cooling start
- ITMY
5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm
- ETMY
5/17~: tuned off ETMY cryostat cooler
- Long term:
- 4/22-5/31: Yarm commissioning
- 5/27-6/30: DRMI commissioning
- 7/1-8/9: DRFPMI commissioning
- 8/12-10/4: DRFPMI ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- Wednesday noon, we will have a Run meeting.
Night work
Weekend
Report of work
- Pressure of ITMX suddenly increased from yesterday. Needs finesse measurement when pressure becomes stable.
Work plan
- COM plan:
- Alignment recovery including AS port.
- Modulation frequency measurement.
- Trial lock of Michelson.
- AOS: Installation for TMS will start from today.