2019/7/5(Fri.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- 7/4: Turbo pump on
- ETMY
- 7/4: Turbo pump on
- Long term:
4/22-5/31: Yarm commissioning
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- Please reduce the number or speed of 16kHz channels.
- GV of BS side can be opened on 7/5, but still please do not oped are side.
Night work
Weekend
Report of work
- VAC: Turbo pump are tuned on for ITMY and ETMY yesterday.
- COM: During X arm lock, dropping transmitted light power was seen by factor of ~2.
- Instability was seen on locking X-arm
Type B: Aluminum foil wind shield for OpLev is being put on SRM now.
- CAL: MICH calibration is going on.
- PEM: Whether information is now recorded into the frame file.
- Noise budget for PEM by turning on/off pump switch will be done today.
- Finding beam position program is being implemented.