2019/7/13(Sat.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- 7/4: Turbo pump on
- ETMY
- 7/4: Turbo pump on
- Long term:
4/22-5/31: Yarm commissioning
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- Please reduce the number or speed of 16kHz channels.
- GV of BS side can be opened on 7/5, but still please do not oped are side.
Night work
Weekend
Report of work
- OLTF of MICH is being measured for ER2.
DGS: 16Hz comb was seen at BS OpLev at lease, so restated daqd, the fixed.
- CAL: Low latency data transfer test will be done during ER2.
- Infrastructure should be prepared well like data transfer, low latency...
- DET: Omicron trigger is ready. Low latency signals should be almost real time, before joining O3.
- DAT: Offline data analysis takes ~1day delay.
Work plan
- PEM: Environmental signal injection is planned after ER2 done.
- CAL: Hardware injection is planned after ER2 done.
- Needs ~30min for PEM, few min for CAL. Actuator efficiency of ITMs.
- SEO: Needs check list before going observation mode. Entering mine.
Public data alert notification in the control system by speaking-> low latency group + DET