2019/7/17(Wed.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan.
- Please write down klog when your work is done and if you will have something to be announced.
Night work
Weekend
Report of work
- Y arm mass lock had some progress on suppressing error signal. Not
Work plan
- Coil driver for mass lock will be upgrade to have more current.
- SR3 noise will be checked and probably power supply will be exchanged.
- OMC will be extracted in the morning.
- DGS: maintenance for exchanging DC power supply for IO chassis for SR3 and SR2.
- Team PC exchange will be postponed.
- Type A model will be restarted.