2019/7/22(Mon.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan.
- Please write down klog when your work is done and if you will have something to be announced.
Night work
Weekend
Report of work
- IOO: Demodulator for iMC was exchanged as a part of CALM loop (Enomoto).
- A new IFO configuration was implemented.
Work plan
- SR3 needs some work for noise hunting.
- OMC work.