Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
Night work
Weekend
Report of work
- COM: Hand off to TRX was succeeded in!
- ITMY: F0 motor on ITMY was stuck.
- We decided to open the chamber to fix the motor.
- One of the dropped magnet of IM on ITMY will be glued.
- It seemed to be another magnet was off.
- OMC axis was not perfect, but it is turned out not easy to tune the axis by hand without jig.
Work plan
- Remaining TF of ITMY will be measured this morning.
- Cryo cooler valve exchange (Kimura, Ushiba)
- Venting will start.
- Type A work (Fujii)
- SR3 TF measurement (Fabian)
- Automation for SR3 and SRM (Shoda)
- Noise source by cable or something in the center room (Yokozawa)
- Setting magnet meter at Y end (Yokozawa)