Commissioning Strategy Meeting (2023/2/17)
- 3 months + 1 week to O4a start (24 May) - Golden Week holidays(3-7 May)
- GWADW2023 (21-27 May)
 
- Daily commissioning strategy is necessary! - More precise time sharing and assignments are necessary.
- Can we work in KAGRA from am 5:00 ?? -> Consult with Ohashi-san 
- How much late is allowed in the night?? -> Consult with Ohashi-san 
 
- Topics on the sensitivity enhancement - Seismic noise isolation of OMC?? (~ 6 months??) - where is the noise due to the "normally expected" seismic noise?
- Some selection - no opening vacuum tanks <- low seismic noise environment to realize 1-3Mpc 
- opening vacuum tanks <- if scattered light ? new injection path is also possible. 
 
- TMPs were off on OMC/SRM at present.
- Seismic noise is still larger than O3GK now.
- Can we reach the O3GK sensitivity level if we can realize the low seismic noise level? -> Washimi-kun -> We can reduce or not 
- If we open OMC, what should we check? - scattered light on the cable? that was identified by Akutsu-kun.
- Bleade spring resonance? No data.
- Up conversion noise implies scattered light noise? - OSTM swing to check the scattered lights? -> Ushiba 
- Slow actuation of suspension -> PEM team 
- Hummering/acoustic test?
 
 
- stable noises also exist.
 
- 3 mirrors(IX, IY, EY) cooling(~2 months(assuming "1 month for one mirror" and "one cooling in one arm at the same time".) - How much commissioning time will be used for - suspension height adjustment
- drifting
- PY/L coupling adjustment
- resonance mitigation control in -> minor adjustment is enough, mainly in gain. 
 
- What is the milestone 
- Cryocooler effects is serious or not? According to Yamada-kun's thesis, no effect for the designed sensitivity. - We can check by just operating motors.
- We get peak noises nad enhanced noises for the frequency range of 10~100Hz.
- Seismic noise comparison?
 
- Can we cool during O?
 
- How much commissioning time will be used for 
- Control of PRFPMI+DC - ADS/ASC/WFS for arms to mitigate the contrast fluctuation -> Ushiba - mysterious off set problems
- under investigation.
- Check the TMSX to kill scattered light.
- ETMY covering -> check effect 
- ADS in FPMI
 
- Enhance OMC lock-acquire stability? - more guardian improvement(Ushiba, Aso)
 
- More dynamic range of PNC-X?
 
- Laser - HPL usage for IFO (120W to Toyama U, Characterized New 60W to KAGRA) - After noise-hunting
 
- HPL in Toyama U (new 60W characterization -> KAGRA, Repair of 120W from KAGRA) - Laser power increase strategy -> Arm cavity instability mainly of Pitch. - Many measures were prepared. So this pitch can be suppressed. Not so serious.
 
 
- What is the milestone to change HPL - 1Mpc ?
- noise budgeting?
- PLL adjustment is bothering us!!
 
- ISS - below 3Mpc line. However, bad alignment will produce a line noise.
 
 
- HPL usage for IFO (120W to Toyama U, Characterized New 60W to KAGRA) 
- Noise hunting, reduction, budgeting - MICH - noise budgeting is important.
 
- PRCL - noise budgeting is important.
 
- Suspension control around <100Hz for some suspensions - local control optimization(filter correction) to reduce the contrast fluctuation? -> Ushiba + alpha 
- no problem in IMC controls
- we need a summary!!(http://172.16.34.76/past_data_viewer/fig_nb/2023/0215/noise_budget_2023-02-15_12:05:26.png) - upload this link in JGWdoc/Dac wiki? -> Yuzurihara-kun 
 
 
- Suspension control around the micro-seismic area - try the bottom filter dumper sensor correction in L
- Terrence method trial in future
 
- PEM/DetChar activities
- Whitening filter apply
- REFL power up
 
- MICH 
- MISC - Remove unnecessary stuff from the isolated area, especially around OMC. -> Miyoki 
- OMC: some cabling should be reset. -> Miyoki 
- Environment cleaning. -> Miyoki 
 
 
- Seismic noise isolation of OMC?? (~ 6 months??) 
- Topics on maintenance for the long operation - Vacuum stuff - Ion pump operation estimation -> Who (Kimura, next week) -> Next week schedule. 
- -> do as soon as possible. 
- TakahashiR-san maybe. + Takahashi-san, Yasui-san
 
- Cryo-coolers
- Air conditioning Coolers/heaters -. Miyoki
- Seasonal water drainage - Yarm pumping mid March - mid May
 
 
- Vacuum stuff 