Commissioning Strategy Meeting Commissioning Strategy Meeting (2023/2/17)
Line 3: Line 3:
 *3 months + 1 week to O4a start (24 May)
  *Golden Week holidays(3-7 May)
  *GWADW2023 (21-27 May)


 *Topics on the sensitivity enhancement
  *Seismic noise isolation of OMC?? (~ 6 months??)
   *where is the noise due to the "normally expected" seismic noise?
   *Some selection
    *no opening vacuum tanks <- low seismic noise environment to realize 1-3Mpc
    *opening vacuum tanks <- if scattered light ? new injection path is also possible.
   *TMPs were off on OMC/SRM at present.
   *Seismic noise is still larger than O3GK now.
   * Can we reach the O3GK sensitivity level if we can realize the low seismic noise level? -> Washimi-kun -> We can reduce or not
   *If we open OMC, what should we check?
    *scattered light on the cable? that was identified by Akutsu-kun.
    *Bleade spring resonance? No data.
    *Up conversion noise implies scattered light noise?
     *OSTM swing to check the scattered lights? -> Ushiba
     *Slow actuation of suspension -> PEM team
     *Hummering/acoustic test?
   *stable noises also exist.


  *3 mirrors(IX, IY, EY) cooling(~2 months(assuming "1 month for one mirror" and "one cooling in one arm at the same time".)
   *How much commissioning time will be used for
    *suspension height adjustment
    *drifting
    *PY/L coupling adjustment
    *resonance mitigation control in -> minor adjustment is enough, mainly in gain.

  *Control of PRFPMI+DC
   *ADS/ASC/WFS for arms to mitigate the contrast fluctuation -> Ushiba
    *mysterious off set problems
    *under investigation.
    *Check the TMSX to kill scattered light.
    *ETMY covering -> check effect
    *ADS in FPMI

   *Enhance OMC lock-acquire stability?
   *More dynamic range of PNC-X?

  *Laser
   *HPL usage for IFO (120W to Toyama U, Characterized New 60W to KAGRA)
   *HPL in Toyama U (new 60W characterization -> KAGRA, Repair of 120W from KAGRA)
   *ISS

  *Noise hunting, reduction, budgeting
   *MICH
   *PRCL
   *Suspension control around <100Hz for some suspensions
    *local control optimization to reduce the contrast fluctuation? -> Ushiba + alpha
   *Suspension control around the micro-seismic area
   *PEM/DetChar activities

  *MISC
   *Remove unnecessary stuff from the isolated area, especially around OMC.

 *Topics on maintenance for the long operation
  *Vacuum stuff
   *Ion pump operation estimation -> Who (Kimura, next week) -> Next week schedule.
   * -> do as soon as possible.
   *TakahashiR-san maybe.
  
  *Cryo-coolers

  *Air conditioning Coolers/heaters

  *Seasonal water drainage
   *Yarm pumping mid March - mid May

Commissioning Strategy Meeting (2023/2/17)


  • 3 months + 1 week to O4a start (24 May)
    • Golden Week holidays(3-7 May)
    • GWADW2023 (21-27 May)
  • Topics on the sensitivity enhancement
    • Seismic noise isolation of OMC?? (~ 6 months??)
      • where is the noise due to the "normally expected" seismic noise?
      • Some selection
        • no opening vacuum tanks <- low seismic noise environment to realize 1-3Mpc

        • opening vacuum tanks <- if scattered light ? new injection path is also possible.

      • TMPs were off on OMC/SRM at present.
      • Seismic noise is still larger than O3GK now.
      • Can we reach the O3GK sensitivity level if we can realize the low seismic noise level? -> Washimi-kun -> We can reduce or not

      • If we open OMC, what should we check?
        • scattered light on the cable? that was identified by Akutsu-kun.
        • Bleade spring resonance? No data.
        • Up conversion noise implies scattered light noise?
          • OSTM swing to check the scattered lights? -> Ushiba

          • Slow actuation of suspension -> PEM team

          • Hummering/acoustic test?
      • stable noises also exist.
    • 3 mirrors(IX, IY, EY) cooling(~2 months(assuming "1 month for one mirror" and "one cooling in one arm at the same time".)
      • How much commissioning time will be used for
        • suspension height adjustment
        • drifting
        • PY/L coupling adjustment
        • resonance mitigation control in -> minor adjustment is enough, mainly in gain.

    • Control of PRFPMI+DC
      • ADS/ASC/WFS for arms to mitigate the contrast fluctuation -> Ushiba

        • mysterious off set problems
        • under investigation.
        • Check the TMSX to kill scattered light.
        • ETMY covering -> check effect

        • ADS in FPMI
      • Enhance OMC lock-acquire stability?
      • More dynamic range of PNC-X?
    • Laser
      • HPL usage for IFO (120W to Toyama U, Characterized New 60W to KAGRA)
      • HPL in Toyama U (new 60W characterization -> KAGRA, Repair of 120W from KAGRA)

      • ISS
    • Noise hunting, reduction, budgeting
      • MICH
      • PRCL
      • Suspension control around <100Hz for some suspensions

        • local control optimization to reduce the contrast fluctuation? -> Ushiba + alpha

      • Suspension control around the micro-seismic area
      • PEM/DetChar activities
    • MISC
      • Remove unnecessary stuff from the isolated area, especially around OMC.
  • Topics on maintenance for the long operation
    • Vacuum stuff
      • Ion pump operation estimation -> Who (Kimura, next week) -> Next week schedule.

      • -> do as soon as possible.

      • TakahashiR-san maybe.
    • Cryo-coolers
    • Air conditioning Coolers/heaters
    • Seasonal water drainage
      • Yarm pumping mid March - mid May

KAGRA/Commissioning/Meetings/Others/StrategyMeeting (last edited 2023-02-17 15:30:37 by miyoki)