Line 31: Line 31:
=== Meetings ===

 * Meeting for pump down at ETMY ([[KAGRA/Commissioning/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * Meeting for closing ETY ([[KAGRA/Commissioning/Meetings/Others/20171117|Minute]])
Line 34: Line 40:
 * [[/CheckList/20171213CoolingETMY|Cooling start at ETMY]] (2017/12/4)

Stage 1

  • Alignment up to BS


Stage 2

  • Align ETMy to IFI (MIF, DGS, VIS, CRY, IOO) with damping
  • Lead MI-REFL beam outside the chamber (MIF, IOO)
  • Install and align MI-REFL output optics using the beam reflected by ETMy (MIF)


Preparation

  • Oplev: 準備は進んでいる。(阿久津)
  • Actuator: 動かせるようになっている。
  • Dampig: センサーの準備をしているところ。PDの光は見えている。
  • RT model:
  • ビームセンターはTcamで見る。
  • 透過光用にBRTはインストールするが、おそらくPhase1では見えない。
  • エンドの物品の準備 -> 和泉

  • 人員手配 -> MIF

Tasks

  • EYCのTypeAとPayload接続完了 (2017/12/1)

  • ETMYでの光確認
  • ETMYのアクチューエターの確認
  • BSのdampingの確認
  • ETMYのdampingの確認
  • ETMYからの光をセンターエリアで確認
  • REFLまでの引きこみ

Meetings

Check list


Stage 3

Tasks

  • Alignment of ETMx
  • Locking of MI with Cryogenic ETMy with Calibrated sensitivity curve


Stage 4

  • Locking of MI in vacuum with cryogenic ETMx/y with data stored


Test run